| Making biogas 2 |
|
PART 2 - Plastic Biodigester Installation Installation Diagram biodigester Plastics are as follows:
Sufficiently important part is the gas outlet. The scheme is as follows: ![]() Outlet Gas Scheme
UV plastic bag (Specifications recommended by the FAO) to, 150 cm wide. Palstik could be obtained on the street Malioboro Yogyakarta. It would be more ideal if the plastic used is yangtebal. Available in the market began to 80cm wide, 100cm, 120cm and 150cm. Please note also the handling of this plastic. UV plastic material is strong enough, but when folded can leave scratches and when exposed to hot sun and rain water can crack and tear. We certainly do not want this to happen. Therefore advised to purchase and handle carefully plastic in rolls, do not be folded. First held plastic mats to protect from sharp objects such as rocks and tree limbs. also caution against metal objects that you take it like a belt, a watch or key chain. These objects can hurt the plastic, so do not wear those things first. including not to smoke. Measure along the 1.5 meter from the edge of the inlet (entrance channel) and mark it with markers. Signs must be right in the middle of the middle plastic, so it is expected the gas outlet right in the middle of the top surface of the plant. Holes should be made slightly larger than the outside diameter of the screw SDL (drat socket outer) gas outlet. If too fitted the plastic tip is feared will be interested when you tighten the socket The next step is to install sewage lines, both incoming and outgoing. This is a step that needs to be done with caution since it requires neatness order not to cause leakage. Can dipergunkanan PVC pipe has a diameter of approximately between 10 - 15cm (3 ", 4" or 6 "and find the quality of AW) should enter and exit the pipe size is the same. The length of pipe approximately 75 - 100cm. Put half of the length of pipe to UV plastic sheet. And with a folding plastic caution becomes one with the pipe (note picture) Bonding begins before the edge of the plastic 25cm (1) toward the outer pipe (2) Make sure the ties are really strong elastic cord, again reminded, a lot of unused rubber strap a rubber brittle and easily broken. You do not want your plant's collapse? Can be in the double bond to strengthen the knot. Noteworthy also is the binding rubber cord must overlap (overlap), and a plastic tip should not be seen, add a few more rounds to ensure tight connections cooperation: Lesman Yayasan Pengembangan Biosains dan Bioteknologi (YPBB)
|